on 05-03-2010 2:18 AM
Dear All,
In Txcode: SM36 -> Start Condition -> click the button >> (located beside "At operation mode") ..
After I key in the Calendar and workday....
may I know what should I key in for the Periods-> Months?
I did press F1 (Duration period (in months) for a batch job) for further details but it is confusing me..
Anyone of you able to explain about what is the Field: Months for ?
FYI, What I trying to do is to schedule a job that will be triggered every second workday of the month.
Best Regards,
Ken
Please follow sap note 16083 for standard basis jobs.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
---> This is for factory calendar days.
Please note: with this method Public holidays, week-ends etc. are taken into account.
may I know what should I key in for the Periods-> Months?
In the months field if you enter "3", the job will repet only for 3 months.
Anyone of you able to explain about what is the Field: Months for ?
Here you define how long the job should run again... (how many months)
FYI, What I trying to do is to schedule a job that will be triggered every second workday of the month.
To schedule the job as you want, set the job as follow :
a) Factory Calendar : XX
b) Workday : 2
c) Time : <Job execution time>
d) Workday relative to: Begining of month
e) Period - Months: 3 (the job will repet next 3 months)
Regards.
Rajesh Narkhede
Edited by: Rajesh Narkhede on May 3, 2010 9:22 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.