on 05-02-2010 3:26 PM
we are looking to implement Charm using solution manager 7 EHP1 with ECC6.0
My question is we have 3 system landscape in ECC(DEV,QA and PRD) and only 2 systems in Solution manager (DEV and PRD)
so is it possible to implement Charm in this situation?
Please let me know the alternatives.
Hello Himanshu,
Additional references you may find very helpful are
Also you might want to look over
> http://service.sap.com/rkt-solman
and
> http://help.sap.com/saphelp_smehp1/helpdata/en/b3/64c33af662c514e10000000a114084/frameset.htm
I hope you find this information helpful.
Regards,
Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks a lot for providing such a nice links to the documentation.
Now My question to the implementers is
1. Is is possibel to implement in Charm automatic transport e.g. as soon as a transport is approved by a change manager to move from Dev to QA system it triggers an automatic transport movement from Dev to QA system
2. As soon as the transport is successfully moved its followed by an email confirmation to the owner as an update that his transport has moved to the respective system
Please update me on this feature
Hi,
Its very much possible to configure Charm.
There is no dependency in manner of landscape design.
You can go ahead with Charm configuration.
Here is the link to start with
/people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
10 | |
10 | |
8 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.