on 04-30-2010 1:38 PM
Hi All,
We need to assign network to Project. But when we assign projet, we get following warning message -
"Network XXXXX and project YYYYY have been summarized in different ways"
Message no. CN771
We have put the "summerization using master data characteristics" indicator true in both project profile as well as network profile.
Please advise,
Thanks & Regards
Shailesh Sontakke
Please check SAP note 128433, 382020.
With Regards
Nitin P.