on 04-29-2010 12:11 PM
Hello,
Currently when you copy a phase and paste it, it copies all the sub tasks, but doesnt copy the responsible role and responsible resource. I need to enhance the coding so that the responsible roles and resources of phases as well as the sub tasks are copied to the new phase/task. I could retrieve the refernce to the phase /task and get the responsible role, but could not add them to the new task.
Can anyone suggest me how to add responsible roles/resources to a task (coding wise)?
Thanks,
Ezhil
Table DPR_BUPA_LINK stores link between role and BP. You can get data from this table
Anuradha