on 04-29-2010 6:23 AM
If i done GR against production order system not assigned automatic qualityplan because in by default system show usage is 5 but GR against Production order Usage is 1 we have to change 5 to 1 then assign specification,so each and every finished material i have to go change inspection lot change usage then assign
Either change the inspection plan through workbench in mass for usage 5 ( or use LSMW)
or
Change the default values of inspection type in customization QCC3>inspection lot creation>default values for inspection type.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thank very much
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Laxmiananda,
Whether it is GR confirmation from production order or Purchase order, the usage will be always 5.
For GR against Purch. Order you use 01 Inspection type, make Inspection plan with usage 5.
For GR against Produ. Order you use 04 Inspection type , make inspection plan with usage 5.
For in process inspection we use 03 inspection type, here GR is not there you have to assign MIC's in Routing with usage 1.
If you do this, inspection plan will be automatically assigned to lot (do ensure that the date of inspection plan preparation is same / prior to that of lot generation)
Best Regards,
Shekhar
Edited by: Shekhar Mokashi on Apr 29, 2010 7:43 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.