on 04-28-2010 10:33 AM
Hello friends
I am not able to create PR,getting error message as budget exceeded for WBS element.
I created the Budget in period 2009,when i see the report CJ31 in period 2009 the values are displaying in period 2010 no values.
Now i creating the PR in 2010 i am getting above budget error.
Can anyone help me in this
Regards
Kiran
You dont have budget for that WBSE in 2010, that is why it is not allowing to create PR...provide Budget for 2010 and then create PR.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kiran,
as per your description I understand that you are trying to post a PR in 2010 but no budget has been allocated for 2010.
Consider doing a budget carryforward from 2009 to 2010 (CJCO) or allocating budget directly in exercise 2010 via CJ30.
Hope this helps
Regards
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kiran,
No, that is not the problem. If the WBS element has no budget assigned, but the superior WBS element does have budget, then the superior object is used as controlling object by means of availability control.
Have you ensured that there is budget allocated in 2010? Have you carried forward the budget from 2009?
Regards
Martina
Kiran,
Can you run report BPFCTRA0 for the affected project and year 2010?
The output of program BPFCTRA0 gives a complete explanation how the assigned value is calculated. It shows a hierarchical list of all objects which belong to a budget carrier (if you expand the list) and an overview of all postings which are included in the calculation of the active assigned value.
You should be able to compare the available budget against the assigned budget and find out the reason why the system does no allow the posting.
Regards
Martina
Martina,
First Level WBS 110444
Second Level WBS 110445
Third level WBS 11044501
under the WBS 11044501 i created internal activities for that activities i attached BOM
For the project 110444 i assigned the budget in 2009,
I created PR for BOM materials in 2009 only.
Now i am trying to amendming the PR in 2010 means today .
The error message:
Item 010 WBS element 11044501 budget exceeded
Item 020 WBS element 11044501 budget exceeded
Regards
Kiran