Hi Friends,
I have a requirement where My client want the ATP check should be done on the basis of followings;
1. Saftey Stocks.
2. Acknowledged Purchase Order
3. Lead Time.
Safety Stock and Lead time is in SAP standard. My problem is Acknowledged Purchase Order..........earlier client was doing on the basis of PO issued. but not client wants to include the PO only when it'll be Acknowleded by the Vendor specifying the estimated date in the acknowledgement.
Share your expertise with me to fix this issue.
Thanks,
NR
Hi,
You can include Shipping notifications in the ATP and exclude the PO. But Order Acknowledgements are not available under the standard scope settings for Availability check.
Regards,
Kathir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For your requirement try using userexit : RV03VFZZ
USEREXIT_AVAILABILITY_IN
USEREXIT_AVAILABILITY_OUT
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.