Reg purchasing department processing time MRP

Is The purchasing department processing time defined for the plant is taken into consideration by MRP while calculating purchase requisition release date??? If not then what is the use of this ? [Where do we configure this in SPRO] ?

SAP help says ..

The planned delivery time from the purchasing info record and the GR processing time are only taken into account if the purchase requisition was generated via materials planning.