Hi,
We need to include two new charateristics in the MPOS. I had first deactivated the PA. Then when try to deactivate the POS, it gives " Planning object structure deactivation failed " Message no. /SAPAPO/TSM792.
I have cleared all the forecast in /SAPAPO/AC05. But there are other time series like Sales order, Purch. order. Stocks.
Should this also be deleted and then I can deactivate POS???
What else needs to be checked to deactivate the POS?
Thanks
Aswath
Dear Aswath,
The error /sapapo/tsm 792 is because the planning area related
to the planning object stru is used in a consumption group.If you
remove the planning area from the consumption group you can
deactivate the POS.
Please check in transaction, SPRO->demand planning->basic settings->
Maintain consumption group, the planning area is linked to
the consumption group.
Hope this will clarify your issue.
Regards,
Tibor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Please delete all the time series objects in the planning area and then deactivate the MPOS.
Warm regds,
Ashutosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.