on 04-26-2010 1:29 PM
Hi,
One of our users trying to close the project but the error is " WIP in financial accounting is still to be cleared/settled". I have checked the report S_ALR_87013568, WIP is zero. I asked the user to run RA and settlement again but could not help. And also checked the relevant threads in this forum but did not get the relevant help.
Could some one help
Regards,
Laxminarsimha
Hi ,
When you run RA and Settlement does system throwing any messages?
And what are the settlement profile parameters ? Are you using any allocation structure ? if Yes have you checked whether all the cost elements and revenue elements have been mapped ? Also are you using COPA ?
Thanks,
Sai.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
make sure that all the actual postings are settled.
Also check if there is any open PR/PO, in that case short close all the PR and PO.
Then try to close.
ashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I am trying to close these projects forcefully because all these are very old and we can't open that period. When I tried to close, I got a message "There is still WIP for WBS" message no KD 450. Then I added my name in OBA5 for this message from error to warning. But still I am getting this error.
Regards,
Laxminarsimha
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.