Is it posible to call succesive 2 Operation Mappings in one Scenario without a BPM?

I want to realize a scenario where i have a basis software component which does standard mappings and hold all messagetypes etc. and customer software component which allows to customize the mapping result in a own SC with a own mapping step without changing the basis SC.

Is it posible without a BPM or what could be a good solution to achieve this?

Accepted Solutions (1)

Accepted Solutions (1)

Shabarish_Nair
Active Contributor
0 Kudos

Why dont you add two mappings to the same OM.

the mappings will then execute in serial.

Guess that is you requirement.

Answers (3)

Answers (3)

Former Member
0 Kudos

thx

Former Member
0 Kudos

You can put several OMs into your Interface Determination in the IB.

So you have 1:n messages.

Cheers

André

Former Member
0 Kudos

We have very much Customers and we want to have a standardized Basis SC which should not be customized by the customers, so that we can easily maintain this SC (versioning etc.) and easily maintain our standard process.

If the customer needs further enhancements he could do this in the customer SC constructive on the mapping result of the basis SC.

stefan_grube
Active Contributor
0 Kudos

> If the customer needs further enhancements he could do this in the customer SC constructive on the mapping result of the basis SC.

This will not work. When the customer enhances the data structure, the standard mapping will ignore the additional fields, they cannot be restored in a second mapping step.

If you enhance the standard data structure, you have to modify the standard mapping also.

Former Member
0 Kudos

Hi Mamba,

To put it simple...

It's nt possible....

U shld use BPM for this.

Babu