on 04-23-2010 6:15 PM
ALL,
To transfer master data between ECC-EWM we use CIF, but I would like to understand the complete EDI setup that is to be done between EWM and ECC.
Any help is appreciated
Regards
Kiran V Yarlagadda
Edited by: kiranvyarlagadda on Apr 23, 2010 7:15 PM
Hi Kiran,
A.To transfer master data like customer /vendor / material,will have to use CIF[core interface] technology.For this you have to do 2 steps.
1.Create integration model for customer /material/vendor and Tcode: CFM1
2.Activate the integration model and tcode : CFM2
This will create new master data/ move changes in master data to EWM.This 2 steps needs to be performed daily.Better way is to set up a daily job for this.
B.To transfer transaction data delivery details/ PGI confirmation / stock changes , SAP has provided standard Idoc type as
1.SHP_OBDLV_SAVE_REPLICA02 to drop order to EWM from R/3
2.MBGMCR for posting/stock change
3.SHP_OBDLV_CONFIRM_DECENTRAL03 for PGI confirmation to R/3.
and some more exists.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.