hello

Is there anywhere in PS or in PM some option to get confirmation from PM order to activity in PS network?

If anyone confirm PM order and the order is technically completed or completed. I would like to automatically transfer status of PM order to activity which PM order is refrenced. If PM order if completed the activity should be automatically confirmed. If PM order is not completed I can't finally confirmed the activity.

I only ask about standard configruration not about ABAP.

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

not possible in standard SAP

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear friend,

in IMG of PS module you can set sub networks as maintenance orders.

ps-structures-operative structures-network-define parameters for subnetwork.

Regards,

Pardhu

nitin_patoliya
Active Contributor
0 Kudos

Subnetwork as functionality is there But from PM order to Netwrok activity is not having any link with respect to System Status pass on.

With Regards

Nitin P.

Former Member
0 Kudos

Hi,

As mentioned by Virendra,

In standard SAP its not possible.

There may be other subnetworks/PM Orders attached to NWA OR else Network Activity has it own confirmation data.