Dear All,

I have been put into a situation adn I seek forum to help me out. Our current solution manager RFC is already set and seems to be working fine.

Issue: I am supposed to create a project for configuration in CRM and generate project docuemtnation from solution manager.

Current status: I can view business scenarios in solar01.

Help required: I need process and configuration steps to to set system to enable me to do configuration and generate blueprint through solution manager.

Hope to get you help.

Accepted Solutions (0)

Answers (1)

Answers (1)

Aru
Participant
0 Kudos

Hi

You can activate the ChaRM for project by enabling the chaneg request management switch under system landscape in solar_project_admin for the particluar project and generate the task list

As you mentioned the all the business process are ready in solar01(blueprint) you can do the configuration in the T-code solar_02 for the corresponding business scenarios

Regards

Arumugam

pratik_mahendra
Contributor
0 Kudos

Dear Arumugham,

I was hoping for little more explicit answer. Treat me like infant in solman. I need steps one after the other. I almost know nothing in solman.