Hi,

I am setting up plan driven procurement.

My Pur Req from the back end are transferred to SRM using the report BBP_EXTREQ_TRANSFER.

It shows that the Pur req has been transferred to SRM.

However i am not able to see the external reqirement in sorcing cocpit.

i hav setup the entry channel, purchase group and responsibility.

Pls let me know how i can track what happened to the external reqest from the ECC system.

Thanks,

Vignesh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hello,

check the outbound queue in ECC using SMQ1. if PR got stuck due to error in transfer to SRM, then check in SRM, SLG1 transaction to get the error encountered.

regards.

Former Member
0 Kudos

Hello Vignesh,

Give the following a try: transaction SLG1 -> BBP_EXTREQ , these provide you the loggings if there were any.

Kind regards,