on 04-22-2010 5:59 PM
Hi,
I am setting up plan driven procurement.
My Pur Req from the back end are transferred to SRM using the report BBP_EXTREQ_TRANSFER.
It shows that the Pur req has been transferred to SRM.
However i am not able to see the external reqirement in sorcing cocpit.
i hav setup the entry channel, purchase group and responsibility.
Pls let me know how i can track what happened to the external reqest from the ECC system.
Thanks,
Vignesh
hello,
check the outbound queue in ECC using SMQ1. if PR got stuck due to error in transfer to SRM, then check in SRM, SLG1 transaction to get the error encountered.
regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Vignesh,
Give the following a try: transaction SLG1 -> BBP_EXTREQ , these provide you the loggings if there were any.
Kind regards,
Tim
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.