Dear All
When I try to create easy cost planning on WBS level by click button ECP system open screen "Edit Costing" instead of "Create cost estimate" When I try to enter version 0 & costing variant PS06 system give error message version 0 not for Easy Cost Planning. First I don't know why system open screen "Edit Costing" instead of "Create cost estimate" please anyone give inputs on same.
Regards
Hi,
How are you accessing ECP? Is it through transaction CJ9ECp or from the WBS detail screen (Shift+F11)?
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check whether you have defined a CO version for your respective Co Area.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pramila,
Please try to check weather the Version is defined for the CO.
In SPRO path, goto Project systems -> Costs -> Planned costs ->Easy Cost Planning and Execution Services - > Easy Cost Planning -> Define CO Versions for Easy Cost Planning
Best Regards,
Punith.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.