MTO & MTS scenario

Former Member
0 Kudos

Hi,

I am having a requirement where my final product ius MTO and input products are MTS..

PPM is defined at all levels, when a Sales Order is created for the final product and I take a CTM run Order segment is created for that order and corressponding Planned Orders are created at subsequent levels which are assigned to the same order segment eventhough the input material is MTS.

I just wanted to know in this scenario can we generate Planned Order for MTS material which will not be assigned to any order segment and which can be pegged to any MTO Sales Order for the final finished component.

I am using CTM for planning.

Thanks & Regards,

Sanjog Mishrikotkar

Accepted Solutions (1)

Accepted Solutions (1)

digambar_narkhede
Contributor
0 Kudos

Hi Sanjog,

Please refer to SAP thread [Sales Order on 1 product and Need to consume Forecast on another product|] .

here forecast product is MTS and Sales order product is MTO.

You can map a planning material scenario to achieve this.

Regards,

Digambar

Answers (0)