on 04-21-2010 6:57 AM
Hi
i am using dip profile to transfer project cost to Quotation in that i can able to transfer all the activity cost but i can't able to transfer the general activity cost.Please give valuable input to me.
regards
Raj
the general cost activity is planned against a cost element - this would be a default entry in your network profile.
In the DIP profile you need to set up the characterisitic - cost element - like activity type (which is working for you)
Then set up a DIEN material and use the cost element as a source
This way your cost activity will be covered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
please elaborate your requirement
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.