on 04-20-2010 12:27 PM
Hi, all
Is it possible to make a periodic back ground job to specific time? (ie, run job hourly from 08:00 to 19:00, everday)
I don't define backgorund job to offline time of legacy server.
Thanks
Yes.
In your example you can use 'No Start After 'and specify the time duing the day that you don't want it to start. after
You can also investigate the use of 'At operation mode' and test these scenerios, always before moving to Production.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think modifying program is best choice.
Thanks all
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can also
define 12 daily jobs job_8, job_9,..., job_19. Not very convenient but it works.
or
use CPS the SAP external scheduler.
Regards,
Olivier
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Maybe via a specific calendar.. Check transaction scal.
Kind regards,
Mark
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.