Validation for NWA confirmation

former_member214674
Contributor
0 Kudos

Hi,

I am looking for validation or user exit at network activity confirmation level. That should check whether price is maintained for activity type if not then it sould restrict users to confirm network activity or even raise an error. Please suggest ?

Thanks in advance.

Regards

Aby

Accepted Solutions (1)

Accepted Solutions (1)

former_member225645
Active Participant
0 Kudos

Aby,

As standard, you would not be able to make confirmation against a network activity unless you have activity type pricing maintained for the work center. Isn't true?

thx, Mathavan

former_member214674
Contributor
0 Kudos

No. System would give only warning message that "Actual cost is not calculated check check log" and that though while saving the project not at confirmation screen.

virendra_pal
Active Contributor
0 Kudos

When you post the confirmation and run the transfer transaction you should get error that cost could not be calculated.

You will not see the posting of the confirmation on the network activity.

After setting the rates, you can then process the actual cost errors.

Answers (2)

Answers (2)

former_member214674
Contributor
0 Kudos

Thanks to all.

Former Member
0 Kudos

In OPST, you can do the configuration for logs/error handling. Whenever there is an error in calculation of cost error log will be generated.

The further setting of "Termination for Incorrect Act cost' will terminate the confirmation itself.

Thanks

Sarang

former_member214674
Contributor
0 Kudos

Sarang, These setting are already done but I can still save confirmation without actual cost.

former_member203108
Active Contributor
0 Kudos

Try this ext :CONFPS02 , it performs customer specific checks during saving of confirmation