on 04-19-2010 7:10 AM
we can't raise PO against approved PR, our budget is 33000, actual+commiment is 2000, but because remordplan is only adjusted based on value, not quantity.because of price difference in the remordplan , we can't raise PO, how to change the configuration or setup to be able to raise PO? thanks