dear all:
Can reservition of 221, take up the wbs budegt?
if it can, take up the budegt ,which factors will effect this?
thank you !
regards!
Movement type 221 is good issue to project, So, It will take up budget based on scenario(Project stock Q or not ) it will check for budget.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I want to confirm:
System will not checking budget during creating reservation to WBS( movement 221). System checking the budget during creating reservation to network activities.
There is no provision in SAP where the budget availability control happens at the reservation level.
Is that right above?
Yes. As I understand, System will not check budget while creating reservation against WBS. System check the same when you create the same against Netwrok activity because here I think concpet of remaining Ord Plan comes in picture.
I think As per design there is no provision in SAP AVAC works at reservation level because Reservations do not generate any commitments in the system.
Quite interesting issue & Observation Someone has difference in opinion or other view please share it will make our undersatnding more clear.
With Regards
Nitin P.