Hi Gurus,

In the SPC criterion, what is the difference between task list characteristic and master inspection characteristic?

Former Member
replied

Ok.. I guess I'm not understanding this last question?

Yes... if you assign a MIC in the plan it also gets a task list characteristic number assigned. What's the issue?

If you pick the criterion of task lisk characteristic then the SPC chart will only contain values from an inspection against this specific task list characteristic, i.e. 0010.

If you pick the criterion of MIC then the SPC chart will contain values from all uses of the MIC.

Not sure what your asking.