A flow has been developed to transfer material (assigned to network activity) from 1 plant to another plant through a stock transfer order with a specific movement type . Find that 'Final issue' on material tab is not getting flagged automatically (and reservation not getting closed) automatically on PGI of delivery from STO.
Like to know the probable reason or the setting which does it automatically on PGI on complete quantity.
With regards,
Mrinal
The reservation created for network activity would be for activity consumption and this reservation will be closed when you issue goods against this network activity, but what you have done is just transferred stock from one plant to another and then how do you expect system to close the reservation created for network activity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ahmed,
We have created a new flow in PS , wherein materials are transferred from one plant to another plant through Stock transport . A new movement type (copy of MT 641) has been created for STO so that the cost is booked on project on PGI from STO Delivery.Materials are assigned to different activities (assigned to different plant) under the same network.
Observe that the reservations on WBS on source plant is not getting reduced on PGI of delivery from STO.
With regards,
Mrinal