on 04-14-2010 10:32 AM
Hi Experts,
I am working with cProjects 4.5, trying to explore printing Gantt functionality.
1. If I try to print a whole project, at the beggining of the graphic I have a gap of approximately 1,5 months before the project starts. How can I print the graphic view only from the project start date?
2. If I had already completed phase 1, maybe printing that phase is irrelevant for me, and I want the graphic printing to start from phase 2. Can I choose a date from when I want to print the graphic?
Thank you in advance.
Best regards,
Neil
Hi Experts,
There are some notes to be implemented about this topic for version PPM45. In PPM50 it is solved.