Hi,

Can someone tell me how I can get the Delivery order to be auto spool when User completed the post goods issue?

Do I need to add in customize coding or can I configure it?

Thanks

Bye

Accepted Solutions (0)

Answers (2)

Answers (2)

colin_cheong
Contributor
0 Kudos

Thanks.

This is beautiful.

I will have to set up another procedure as the practise is only limited to certain delivery order type.

Former Member
0 Kudos

Hi,

I understand you are trying get a delivery related output type triggered on goods issue of the delivery. There are essentially 2 settings to be done: -

1. In SPRO configuration, for the delivery output determination procedure, enter Requirement '1' against the delivery output type.

2. In VV21/VV22, when maintaining the delivery output condition record, use the timing as '4' and check the Print Immediately check box in the Communication.

Thanks

Swagat