cancel
Showing results for 
Search instead for 
Did you mean: 

availability check in sales order

Former Member
0 Kudos

Dear gurus

please is there a way i can do the setting so that anytime i create sales order system will authomatically carry out availability check. Right now after we create sales order we go through va02- select the line item- click availablity check - copy - save. this is done so that whenever we carry out MRP open sales order quantity will check for stock availability before it generate a pln order

thanks

Agatha

Accepted Solutions (0)

Answers (4)

Answers (4)

Lakshmipathi
Active Contributor
0 Kudos
i create sales order system will authomatically carry out availability check.

This depends on your schedule line category. First identify what schedule line category is flowing in your sale order. Next go to VOV6, select your schedule line category and execute. There tick the box for "Availability".

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi,

Availability check

u2022 An Availability check is carried out during sales order processing.

u2022 An availability check occurs if-

􀂾 The Material requires an availability check-in material master (Gen./Plant or MRP 3)

􀂾 The Material availability checks in customizing-Delivery item Categories and Schedule line

categories.

u2022 Availability is checked on material availability date. The material availability date is

determined from delivery scheduling, on this date enough material has to be available in time for

delivery to the customer for their requested date.

u2022 In Customizing, you can configure which inward and outward movements are to be considered in

availability check.

u2022 Communication between sales and distribution and Procurement is carried out via requirements. The

transfer of requirements type can be influence the availability check.

u2022 Any agreements made with customer about deliveries also affect the result of the availability check.

Example-complete/partial deliveries.

u2022 The indicator for controlling complete/partial deliveries is proposed from the customer master

records. The proposal for the item level comes from the customer-material information record, if

a customer and material agreement maintained there. These indicators can be changed manually

during order entry.

u2022 The availability check includes-

􀂾 Current stock

􀂾 Inward movement

􀂾 Outward movement

Backorder processing

u2022 An order item is backdated if

􀂾 The quantity of an order item is not totally confirmed.

􀂾 The request delivery date for an order item cannot be kept.

u2022 There are two type of backorder processing

􀂾 Manually- From list sales order processes them manually with reference to confirmation (Short

fall can be cleared).

􀂾 Via Rescheduling- We can use the delivery priority (proposed from the customer master) and

make new order and confirmation date by scheduling.

Regards,

Former Member
0 Kudos

you can fulfill this requirement very easily..........

1. you material master availability check should be give as requirement 02(individual requirement)

2. Schedule line category should be activate for availablity check.......

thats all.it will fulfill your requirement.

all the best.

revert back to me..for further clarification if needed

Former Member
0 Kudos

Av check in order is performed based on the requiremnets class, requirements types and avalability check setting in the material master data AND / OR Item Schedule line category settings.

Please check this link:

http://wiki.sdn.sap.com/wiki/pages/viewpage.action?pageId=29323

Few Transaction codes related to ATP: Please do the necessary settings

1.Allocation Procedure (OV1Z)

2.Allocation Object (OV2Z)

3.Allocation Hierarchy Mapping (OV3Z)

4.Define Consumption Periods (OV5Z)

5.Control Product Allocation (OV4Z)

6.Activate Allocation for Requirement Class (OVZ0)

7.Activate Allocation for Schedule Line Category (OVZ8)

8.Create Planning Hierarchy (MC61)

9.Generate Masking Character (OV7Z)

10.Modify Planning Hierarchy (MC62)

11.Allocation Procedure Assignment to Material Master (MM02)

12.List of Suitable Structures (OV9Z)