on 04-13-2010 8:16 PM
Hi
How is SD integrated with PP since my sale order should give the required quantity intent to my production dept, at the availibililty check level at my sales order how it is done in SAP
Vinz
Hi,
Make-to-order production is controlled by the requirements type. The requirements type is determined on the basis of the MRP group and the strategy group in the material master record.
Regards,
Seegal