on 04-13-2010 9:51 AM
Hi experts!:
I have the next question..
I want to make the production startup of Material Ledger module, but I have read in a note of SAP that recommend to make the next action:
" Before starting the production startup, close all manufacturing orders and create new orders after the upgrade. For already
existing production orders, there is no connection to the material ledger quantity structure tool during the production startup.
That means that these orders are not taken into consideration during multilevel calculations."
Is there any way to do a Manual Reposting of Cost between two manufacturing orders?
Best Regards!!
Manuel
Did you try Tcode KB11N...??
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
At first thanks for all...
But this solution not cover all that I need because I need to reposting the Cost but I need to reverse the Backflush quantity in repetitive manufacturing too, because if I don´t reverse this, I will have the same quantity in the old order and in the new one.
I will need a solution which permit reposting at both concepts...the Costs and the Backflush quantity..
Thanks and regards!
Manuel