on 04-13-2010 3:39 AM
Hi Guys,
We have an issue - i.e. when we create STO manually in ECC 6.0 it always add extra one day to the good issue lead time. I have checked and we have no plan delivery date on the material master, 'pick & load' at the shipping point is standard 1 hr, no lead time on the route. Also as this is intercompany STO so we do not use PIR.
Any ideas where can this one day extra lead time comes from?
Thank you.
Please check if there is a lead time defined in the material master and also if there is any GR time listed in the material master for the plant you are shipping too.,
please let me know if this solves your issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks kiranvyarlagadda. I have checked and we have no planned delivery time nor GR time at the material master for both supplying and recieving plant. I noticed that in the STO, under the shipping tab there is a 2 days planned delivery time. However, the planned delivery time in material master is 0 and we did not create vendor/PIR for the receiving plant. We can't figure out where this 2 days coming from...
Edited by: SapBusinessUser on Apr 14, 2010 4:28 AM
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.