Intercompany STO lead time

Former Member
0 Kudos

Hi Guys,

We have an issue - i.e. when we create STO manually in ECC 6.0 it always add extra one day to the good issue lead time. I have checked and we have no plan delivery date on the material master, 'pick & load' at the shipping point is standard 1 hr, no lead time on the route. Also as this is intercompany STO so we do not use PIR.

Any ideas where can this one day extra lead time comes from?

Thank you.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi ,

Please check Material Master - MRP2 - GR Processing Time

Regards,

Moshe

former_member681791
Active Participant
0 Kudos

Hi,

You may check for shipping point configuration in OVLZ.

Cheers,

Girang

Former Member
0 Kudos

Thanks girang. I have checked the Shipping point configuration and it is standard 1 hr for 'pick & load'. The funny thing was we tried creating STO from the same supplying plant to existing plants in SAP and they worked fine; but this problem occured when we created STO to the newly added plants into SAP. Can't figure out what is the problem...