Is it possible to correct purchase order price after done all process from good receipt to invoice verification, delivery cost positng?
What all values can be changed in PO, and will it have any impact.
It will have some impact from a reporting point of view e.g. PO v invoiced value so you need to consider that but it won't have any impact from a posting/financial point of view.
Regards,
Nick
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Go through SAP Note 456691 - FAQ: Price determination in purchasing
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
yes you can change, but what purpose? as you said GR, IV already done.
If it is open PO it will effect further process. But no effect on already created documents.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Alexandro,
Yes you can change the PO value , but for that you have to cancel all GR & IR entry against that PO .
If you want changes for further GR & IR you can add new line item with new price .
Rgds,
Kareena
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, yuo can get the PO price changed, but it will not have any impact on already existing GR and IR documents. To have impact on them, you need to cancel those documents and recreate them referring the changed PO and then you will have impact on those documents.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.