Dear Gurus ,

I implimented user exit for MRP run for particular MRP controller. Now suppose i have two FERT A & B which are belongs to MRP controller 001 & 002 resp. and C is depedent component for both A & B maintained in BOM . In C 's material master 001 is assigned as MRP controller . so at the time of MRP run for mrp controller 002 depedent requirement for C is not generated , is it not possible to generate depedent requiremtent in both cases i.e when we run mrp for 001 and 002 controller.

please guide me . Thanx in advance.

regards

siva

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Are you using enhancement M61X0001 with function al modules EXIT_SAPLM61C_001 and in EXIT_SAPMM61X_001 and have you defined parameters MRP controller? then use same MRP controllers for these materails. Or else youe the MRP group to plan the requirment of C.

Please refer this link for details,

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear

Thanking you for response i solve this scenerio with creating product groups.

thanking you

regards

siva

Answers (1)

Answers (1)

Former Member
0 Kudos

This is standard SAP behaviour,

if you use exit for MRP controller, only materials for that MRP controller will be planned

regards