Dear All,

Our production is in PP-PI , having

Finished product -- > 2 Semi finished pdts -- > Raw materials

The finished product have one master recipe with 3 phases , one is for finished prodt other two are for semi prodts

Finished prodt BOM has 2 semi finished pdts, process order confirmation by phase

Normally during final phase confirmation of process order, receipt finished product

Some times the successor resource may be downed but predecessor resource mayn't be stopped and producing IPs (Semi Pdts ),

How can we do receipt for semi finished products in to interim stog loc ? during phase confirmation of finished product process order

Here no specific master recipe and process order for semi finished products

Regards

Dev

Edited by: Devakumar on Apr 12, 2010 2:24 PM

Accepted Solutions (1)

Accepted Solutions (1)

Rachel_Tang
Advisor
Advisor
0 Kudos

It may hard to realise it within one single order, you may consider of using collective order for process order, I think that would be proper for your business scenario, you may check more for collective order in:

http://help.sap.com/erp2005_ehp_04/helpdata/EN/b1/c05026439a11d189410000e829fbbd/frameset.htm