PO price changes before the complete delivery

I have an issue..... we have ordered a certain material say 2000 pcs to be delivered over 6 months of time in a PO. The price at the tme of PO date was say 100 INR....now we have GRNd 200 pcs. After 1 month the vendor will charge 105 INR for the same item. Case is price changes keep happening like this almost every month. How to address this issue in PO...?

Former Member
Former Member replied

This can be solved by maintaining Pricing Date Category in PIR. Go thru the following thread

price date category in PIR