Hi experts,

right now, I am facing an issue and I need you help. Thank you.

Here is the case:

we set a batch job to mass processing availability check of production order.

Job parameters: program:PPIO_ENTRY

procduction orders with MSPT status and without TECO status.

Order finsh date within 10 workdays.

but we still found there are some components, even afer the batch job, it still shows as Missing part. I can display from CO24.

I checked MMBE, the stock in sufficient.

I go to the production order, the order with MSPT status and MANC status at the same time, I don't know why.

but after I run availability check in Co02 or COHV manually, the material is committed.

this happens before, and this is one of the reason we create the batch job.

here is the situation, if there is any more infomation needed, I will keep it updated.

Thank you in adv.