import scheduling agrement

HELLO SAPGURU,

in our organisation import po cycle is as follow scheduling aggrement cretion> delivery schedule maintain> miro for custom office --> j1iex for capture and grn for post and miro for normal vendor

but after custom miro when i go for j1iex for capture maintaining scheduling number and custom invoice no.system shows message " scheduling agreement does not contain any selectable item" .

ihave maintain delivery schedule date in me38 of todays date but still it showing same message

please help