Hi Expert's, Could any one tell me the step by step procedure to achieve the dead line monitoring in SRM7.0 Process controlled workflow.
Thanks in advance,
Regards,
Bhanu Gattu.
Hi,
What is your business requirement? It is just sending notification or any special process for deadline?
http://help.sap.com/saphelp_nw70/helpdata/en/c5/e4b97e453d11d189430000e829fbbd/frameset.htm
Alert notification for deadline is available but enhancing process steps for deadline is not available because standard workflow templates are not changable in Process-Controlled Workflow. You can use Application-Controlled Workflow or create custom workflow template for deadline monitoring.
Regards,
Masa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks, Masa for your reply.
My Requirement:
I have to send reminder notification to approver after 2 days. After Second reminder i have to copy SRM admin in the email for third reminder.
How can i achieve this. I have completed all my requirement using Process Controlled workflow, now i can't go back to Application controlled workflow.
Please suggest.
Thanks,
Bhanu Gattu.
Hi,
The solution for your requirement is Alert Notification. It is standard function.
Transaction: SPRO
SRM -> SRM Server -> Cross-Application Basic settings -> Business Workflow -> Process-Controlled Workflow -> Business Process Configuration -> Define Deadline for Events
You can also use the BAdI BBP_ALERTING.
Regards,
Masa