is it possible to assign a project to TRs already released? Those TRs are already in quality system and now they must be imported in preproduction system via ChaRM which is completed only now.

Thanks a lot.

Bob

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

The other option could be, withdraw this change request and create a new change request with the correct project, and merge this released TR with the new transport request.

Regards,

Sneha.

Answers (1)

Answers (1)

raguraman_c
Active Contributor
0 Kudos

Hi,

No you cannot assign a project to a request that is already released (Non Modifiable). remove project mandatory setting in SE03 (if maintained) and manually move them using STMS.