Hi All,

We are implementing SAP WM for one of our customer and we are facing difficulty in mapping the below business scenario in SAP. The scenario is.

1. Putaway for GR:

When they receive wires/cables of a same material in multiple spools with different or same length from the vendor they consolidate all the spools in a GR area and placed in a standard pallet to putaway to the IM location.

Example: 48 Spools (Each 1000 feet) placed in a Standard pallet (48u201D height)

Question u2013 how do we define a palletization data on this scenario and create a 48 different SU labels for each spools (Because we are considering each spool is a separate Storage unit). We have defined a separate Storage type for handling the wires and cables and this is not bulk storage.

The reason we are creating a separate SUu2019s because they do partial picking and based on the requirement we are matching the exact fit or best fit strategy to pick the right SU.

Thanks in advance.

- Praveen

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

How do you want to do with these spools at the end ?

If you want to sort out these spools and datas containing in these spools to make a single .xls or .pdf, i have a solution.

However if you want to merge these spools in a single spool staying in SAP i couldn't help you.