create Asset through WBS/Network

Former Member
0 Kudos

Dear All,

when we create a Asset PR through WBS or Network it is not Updating in Commitment cost, against PR i created PO and then did GRN, but it is not Updating in Actual cost also for the given WBS

So how to create Asset through WBS kindly suggest

Thank you,

Regards,

Naveendra

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member203108
Active Contributor
0 Kudos

Please read this note 61414, it may help you

Former Member
0 Kudos

Hi

For commitment ans Actual Cost Updation please check you cutomization settings.

AUC (Asset Under Construction) gets created once WBSE Element is Released provided that Investment Profile is defined in Project Profile configuration.

Asset number get created after Full settlement of WBSE and Asset Completed.

Please check.

Swapnil Kharul

Former Member
0 Kudos

HI Thank you,

I'm not using investment Profile,i'm creating Direct asset(Mannuel PR creations with "A") that time when we assign asset number and WBS it is not updateing in CJI5 and also Budget is not getting update

Reg

MN

former_member203108
Active Contributor
0 Kudos

Dear, just by creating PR with account assignment category A and assigning WBSE to it alone will not work...You will have to fulfill certain prerequisites and do other settings also....

Please read SAP HELP, this scenario has been explained very clearly in it...

Former Member
0 Kudos

Thank you, Can u Pls send me the link

Thank you,

Regards,

MN

Edited by: Virendra Pal on Apr 12, 2010 11:35 AM

Read SAP Help yourself - don't expect this forum to spoon feed you

matt
Active Contributor
0 Kudos

Naveendradoss, Virendra Pal is a moderator, and has edited your post. What you need to do is follow his direction - not complain about him using the abuse button.

hth

matt

virendra_pal
Active Contributor
0 Kudos

Naveendradoss

Writing abusive email to my personal ID will also not help your cause.

Virendra