SNP Optimiser issue (Annual Planning Run)

Former Member
0 Kudos

Dear Friends,

My fiscal year is 01.04.2010 to 31.03.2011, Now I am trying to run Annual planning run for the current FY.

After the run, If i see in SNPOPLOG, all demand is showing as unfulfilled. If i run for the next FY it is planning.

I want to run for the current FY, what settings I need to do?

sree

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sree,

Check the data view in transation /SAPAPO/SNPOP which you

have selected for running the optimiser whether is it falling

within the planning run period.

Regards

R. Senthil Mareeswaran.

Answers (2)

Answers (2)

nitin_thatte
Contributor
0 Kudos

What is the time bucket profile of data view in which u are running optimizer. If it is a single yearly bucket you cannot run optimizer in current year. (your first bucket cannot have the start date in past)

Choose 12 monthly buckets. and run planning. You may 'view' the planning results in single annual bucket.

even if you do this, there will be no plan in current month. system will plan from next month onwards.

Hope this helps.

Regards,

Nitin

Edited by: Nitin Thatte on Apr 13, 2010 6:01 PM

Former Member
0 Kudos

Also check on the planning horizon used during planning run