Planning Horizon

My client requirement to have plan the materials for 90 days and for some materials 180 days within one plant. I have created two MRP group, One with 90 days & 180 Days as Planning horizon, assign same to the materials. However I am geeting the procurement proposals for all 540 days, which is maintain in the plant parament (planning parameter).

I have removed the planning horizon from plant parameter.

Please suggest.

Thanks in advance.

Sanjay

Former Member
replied

Dear ,

You need to assing the the two MRP groups having PH -90/180 as applicable in the Material Master MRP1 view .Secondly , run the MRP with following set up :

1.MD01/MD02-

Processing Key : NETPL

Create PR -2

Schedule Line -1

Create MRP List : 3

Planning Mode : 3

Scheduling : 2

Diplay Material to be ticked /Display Material before save to be ticked in MD02.

2.All the material should have planning file entry in MDRE.

Regards

JH