Wrong date in MCRE report for unplanned issues

Former Member
0 Kudos

Dear All,

We are on SAP ECC 6.0 EHP4 release post Unicode conversion the S026 infoset / MCRE report is showing wrong qty/values.

The component materials which are not a part of bill of material added at the process order confirmation stage in COR6 transaction are not capturing in the MCRE report.

Additional Info: We have checked the info set S026 the date field is updated with 00:00:0000 for all such unplanned issues. Where as in the earlier version it was capturing current posting date for unplanned issues.

How to resolve the above said issue.

Regards,

Praveen

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Did you get a solution for this? We are facing the same problem.

Kind regards,

Walter

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

First check the setting of OMOD for info-structure S026 for updation.

In transfer structure "AFPO_OLD", field "LTRMI" is not filled. As a result, the system generates a record in S026 with date 00.00.0000

Please refer OSS Note 1320562 - Incorrect updation of S026

Also check the report MCRP.

Else contact directly to SAP.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Brahmankar,

Thanks for the answer. As you told I have gone through the SAP NOTE: 0001320562. It is forRelease 600 to Release 605.

We are into 701 Release. Will this note applicable for us ?

Regards,

Praveen

Former Member
0 Kudos

Hi,

Please refer to note 64636. You need to setup statistical data for S026 info structure.

Regards

Vinod