Hi,

We are assigning the materials in the network internal activities through itemcategory N.Initialy we do not want to generate the PR for the materials in this status.So we are setting the Res/preq field to Never in the procurement paramter tab for the materi.al detail screen in activity,

But when we set the Res/Purc.req to immediately it will generate the PR.Please note that still the status INIT is active,where in generation of PR is forebidden. But still PRS are generated.Please advise.

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Yes ,The reason may be , status profile is not assgined to particular netwrok activity

shashi_kulkarni
Explorer
0 Kudos

In business transaction for purchase requisition shows traffic light is red.But still it generates the PR..

shashi_kulkarni
Explorer
0 Kudos

hi I got the answar..with any of the user status,the creation of PR can't forbidden.There are some transaction which will not be affected by user stauses..

nitin_patoliya
Active Contributor
0 Kudos

Check out of your User status profile assgined to that perticular Netwrok activity, where you aggined network component. And also check customization of your project user status profile which is having INIT staus and check which are the business procedure are forbidden.

Also let us know this behaviours is universal or to specifc project few projects.

WIth Regards

Nitin P.