Plan Monitor

This is a general experience question

Has anyone used the PLAN MONITOR /sapapo/pmon.

What has been your experience? what are the best applications? Any thing to watch out for?

Thanks

George Morstadt

Former Member
Former Member replied

Hi George,

The Plan monitor functionlity can be used in many areas of APO.

From expericene, it is felt that most usefulness can be in the area of Detailed Scheduling of Production Planning module.

Specifically planning situation with scheduling / rescheduling orders . Normally shortterm order adjustments becomes critical than supply adjustment in say 6-10 months down the line.

No experiecne in usage of Plan monitor in CTM.

I hope this gives you some insight.

Regards

Datta