on 04-09-2010 12:09 PM
Hi Experts,
Working with cProjects 4.5, we are trying to create a new project taking as a template a simulation. The projects is correctly created but contraints in the simulation are not copied to the project.
Have you had the same problem? Is it standard behaviour?
Thanks in advance.
Best regards,
Neil
Hi Neil,
It is standard behaviour. The reason is that, during the creation, the project get today as project start, so the constraints in the simulation are typically obsolete, because project-start of simulation is typically not today.
If you need such functionaltiy, please check the Badi method SET_DEFAULTS_UPON_COPYING of
DPR_ATTRIBUTES.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is there any other way to copy schedule?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.