on 04-08-2010 5:46 PM
Hi,
I created a custom FM for the object - MLST_NETW and event STARTED
and in the workflow container I created Element for this object - by selecting Obect type - MLST_NETW
Now the problem is - When we do status change in tcode - CJ20N it is triggering the custom worklfow but in the worklfow container it is not getting any values. Container fields are empty. I need to get the project defination field value to the workflow.
Can any one tell me what could be wrong?
Thanks in advance.
M.
I think there is no binding done from event to Workflow please make the necessary binding from PFTC Tcode.
Thanks
Arghadip
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Murali,
Yes. Binding for event to workflow not defined.
For that, press Ctrl + F8 in the workflow template then it will take you to verision dependent tab. There you can find the start events tab.
Here only you entered the Business object and event. Right? So there one button is there for binding. CLick on it and check whether event to workflow binding has done or not.
Event container EVT_OBJTYPE should binded with your workflow business object.
Thanks.
Hi Rick,
Yes Actually I forgot doing Event to workflow container binding. I thought this will be done automatically.
I did binding now and all the values are showing in the workflow.
But actually I need project definition value from the container. But from the MLST_NETW and BUS2002 I am not getting this value.
From table AFKO by passing network number(which I am getting from workflow) I can get project no.
Thanks for answers.
User | Count |
---|---|
87 | |
10 | |
10 | |
9 | |
7 | |
6 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.