on 04-08-2010 1:18 PM
Getting below msg:
Date 20.10.2011 is after the end of factory calendar 99
Message no. V1086
For this I went to scal and maintained val date till 2015 still getting above msg kindly suggest.
Hi,
There are three calenders in SCAL, have you extend the Factory calender?
Regards,
MT