Dear Sapgurus,

while making of consumption items with cost center K I need check automatically budget availability with out giving CO/PP Order.Please tell me.

Regards

Mydream

Accepted Solutions (1)

Accepted Solutions (1)

iklovski
Active Contributor
0 Kudos

Hi;

There is no budget check in CO for cost centres. You cn make a workaround with statistical internal orders, though.

Regards,

Eli